Project Overview
R. Benson Property Maintenance Ltd were appointed as the principal contractor to undertake the erection of a first floor school extension, with associated alterations at Jessop Primary School, London. The extension comprised of a steel frame which was erected on to the second floor roof space to provide additional teaching, support and office accommodation to include a sound proof music room.
The works had to be planed carefully as the majority of the works were carried out whilst the school was in use. The constraints of the project to erect the school extension meant that we had to work closely with the school regarding noise, traffic management and timed deliveries.
The works consisted of:
- Installation of steel frame and timber infill’s
- Brickwork
- New Langley flat roof with 20 year guarantee
- Internal partitioning and plastering
- Commercial Mechanical & Electrical works
- Sound Proofing
- Floor Coverings
- Decorations
- All internal finishes